Lime Kilns Retrofit

Improvement projects
Reliability
June 2018
Project start
Н2 2021
End of implementation
USD 21.2 million
Volume of investments

About the project

Increase lime output from 800 tpd to 950 tpd

Supply lime to support the increase in mill capacity and supply white liquor to O2D Plant

 

Project objectives

  • Increase capacity
  • Improve equipment reliability

Scope of Work

  • Lime kilns retrofit 

Approved for implementation

Lime Kiln 2 – November 04, 2019

Lime Kiln 3 – November 02, 2020