Rebuild of Recovery Boiler 1
Replacement of the handling line in the Paper Area of the Bleached Kraft Pulp and Printing Papers Production Plant
Efficiency Improvement
Photo
7
Photo
Share on social networks
January 2016
Project start
January 2016
End of implementation
USD 4.3 million
Volume of investments
Project goals
Wrap rolls of large size and diameter
Increase production volumes
Increase profit
Reduce costs
Improve occupational safety
Project scope
Construct a new electrical room
Dismantle the current and install new handling system equipment
Construct rooms for handling system operators